[Updated on June 5th]
Overview
This tracker documents key stages, timelines, and status updates as Dracula: Dark Reign moves through assembly and fulfillment.
Logistics Status
| Parts | Status | Expected delivery date |
| Game Boxes | ✅ Arrived at our assembly line | N/A |
| Instruction Booklet | ✅ Arrived at our assembly line | N/A |
| Sticker Sheets | ✅ Arrived at our assembly line | N/A |
| Cartridge Stickers | ✅ Arrived at our assembly line | N/A |
| Cartridge shells | ✅ Arrived at our assembly line | N/A |
| PCBs | ✅ Production Done |
N/A |
| Inlay inserts | 🛠️ Inserts production ongoing | Mid June |
Assembly Status
| Editions | Status |
| Standard Edition Complete in Box | Waiting for parts |
Fulfillment Status
| Editions | Status |
| Standard Edition Complete in Box | Waiting for inventory |
Changelogs
[May 20th] PCB production updated from 🛠️ In production to ⚡️ Flashing in progress
[May 20th] Inlay inserts updated from 🛠️ Mould in production to 🛠️ Mould finished - awaiting samples
[June 5th] Inlay inserts updated from 🛠️ Mould finished - awaiting samples to 🛠️ Inserts production ongoing
[June 5th] PCBs updated from ⚡️ Flashing in progress to ✅ Production Done